Understand the fundamentals
Installation is not yet verified operation
Installation means placing and connecting equipment by following an approved procedure. Commissioning means proving that the installed equipment works as intended under defined conditions. Seeing a machine’s fans start is one observation. It does not mean commissioning is finished.
Before work starts, confirm the exact model and the approved location. Also confirm the supported power and cooling setup, the network plan, the parts needed and that the task is authorized. The responsible personnel must put the electrical and facility requirements in place. This lesson explains the order of the steps. It is not a physical installation procedure for any site or machine.
See how it works
Connect identity, configuration and observation
After the authorized installation and startup are complete, compare the machine with its records. The asset, location, network identity (such as its IP address) and worker name must all match. Check that the intended firmware (the machine’s software) and operating profile (its chosen settings) are in use. Use the model documentation to confirm that the expected boards, sensors and status appear.
Let the machine finish its documented startup and tuning steps before you judge whether it runs steadily. Then compare the hashrate the miner reports (local hashrate) with the work the pool accepts, over a suitable time window. Confirm that temperatures and alarms behave as expected in the site’s real conditions. A commissioning record should state what was checked and when. The word “works” on its own is not enough.
A baseline connects a measurement to its conditions
Swipe sideways to follow the full diagram →
Connect it to the field
Build a baseline you can use later
A baseline is a record of how a machine ran under known conditions. Include the model and revision (hardware version), firmware, profile, location, key temperatures, local and pool readings, and the time window they cover. It is a reference point for later comparisons. It does not promise that conditions will never change.
For example, say someone later reports a lower hashrate. That is easier to explain if the records show the profile used for the baseline and the profile in use now. Without that, a planned switch to a lower-power profile could be mistaken for a hardware failure. Record every approved change so the baseline stays useful.
Terms used in this lesson
- Commissioning
- The approved process for bringing equipment into service and verifying operation.
- Baseline
- A recorded set of normal readings under known conditions.
- Acceptance
- Evidence that the planned checks were passed, not just that the power is on.
Optional references & further reading
Use current manufacturer instructions for the exact equipment and your site’s approved procedures. Course levels do not grant task authorization.